Most deals die in the refurb budget — usually because it was a guess. These are the ranges we actually see on our own projects and quotes across the South West. Prices assume labour and materials at a solid landlord spec, not luxury and not bodge. Your street, your spec and your builder will move any line — that's what the contingency is for. Treat every number as a planning range, then let written quotes replace them one by one.

How to use this

Use it at viewing and offer stage: walk the property, list the works, price each line from the ranges here, add contingency — and you have a defensible refurb budget before you've spent a penny on quotes.

01

How to use these numbers

  • Price the job from the property, not the sheet: walk every room, list the works, then price the list
  • These are South West ranges at landlord spec — London and the South East run 20–40% higher
  • Three written quotes for anything over £1,000; a verbal number is a mood, not a price
  • Ask every trade the same question: what would make this price change once you open it up?
  • Assume VAT is inside the quote only if it says so in writing — a VAT surprise is 20% of your budget
  • Self-managing trades saves 10–20% versus a main contractor, but costs you time and requires you to sequence the job correctly
02

External works

  • Full new roof, 2/3-bed terrace: £6,000–£9,000 (concrete tile, including scaffold)
  • Roof repairs — slipped tiles, ridge repointing: £300–£1,000
  • New guttering, fascias and soffits, terrace: £800–£1,500
  • Damp-proof course injection plus replastering affected walls: £2,500–£5,000 — diagnose the cause first; half of 'rising damp' is a leaking gutter
  • UPVC windows: £450–£650 per standard unit fitted; whole 3-bed terrace typically £3,000–£5,000
  • Composite front or back door, fitted: £900–£1,400; budget UPVC door £600–£850
  • Full render of a terrace front: £2,500–£4,500; whole house £5,000–£9,000
03

Heating, electrics & compliance

  • Combi boiler replacement, like-for-like: £2,200–£3,200 installed
  • Full new central heating system — boiler, rads, pipework, 3-bed: £4,500–£7,000
  • New consumer unit: £500–£900; if the board is old, price the rewire conversation immediately
  • Full rewire, 3-bed, including making good: £4,500–£7,500
  • EICR: £150–£300 · Gas safety certificate: £70–£120 · Both are legally required to let
  • EPC improvements to hit C — loft top-up, trickle vents, heating controls: £500–£2,500 depending on the starting point
04

Kitchens & bathrooms

  • Landlord-spec kitchen replacement — units, worktop, hob, oven, extractor, fitted: £3,500–£6,000
  • Kitchen refresh — doors, worktop, paint, hardware, keep the carcasses: £800–£2,000
  • Full bathroom replacement — suite, tiling, flooring, fitted: £3,000–£5,500
  • Bathroom refresh — new suite in same positions, minimal tiling: £1,500–£2,500
  • Adding an ensuite — stud wall, plumbing, suite, tiling, plastering: £4,000–£7,000
  • Moving soil pipes or bathrooms between floors: get a fixed quote before you count the deal — this is where budgets die
05

Walls, floors & finishes

  • Plaster skim, average room: £400–£700; full replaster (hack off and re-board): £900–£1,500 per room
  • Hallway, stairs and landing replastered: £800–£1,500
  • Internal doors: £120–£200 each fitted; FD30 fire doors with intumescent strips and closers: £300–£450 each fitted
  • Paint and decorate, average room: £250–£450; whole 3-bed house: £2,500–£4,500
  • Carpet, average bedroom, landlord spec: £250–£400 fitted
  • LVT or laminate, average room: £350–£600 fitted — LVT costs more and outlives three tenancies
06

Structural & everything else

  • RSJ / steel beam including building control sign-off: £1,500–£3,000 per opening
  • New staircase, standard softwood: £1,200–£2,500 fitted
  • New stud partition wall, plastered both sides: £600–£1,000
  • Skips: £250–£350 each — a full 3-bed strip-out fills three to five
  • Garden clearance: £150–£250 per day per person, plus disposal
  • Asbestos survey: £200–£400; removal is quoted per job — never disturb suspect materials to save the survey fee
07

Whole-house rules of thumb

  • Light refresh — paint, floors, tidy, minor repairs, 3-bed: £5,000–£10,000
  • Medium refurb — plus kitchen, bathroom, some plastering and doors: £15,000–£25,000
  • Full refurb — everything: systems, roofline, kitchen, bathroom, full redec: £30,000–£50,000+
  • Contingency: 15% on a light job, 20% on anything structural or pre-1930 — added at the end, spent only on surprises
  • Every week of overrun costs you a week of rent plus finance interest — build the timeline into the budget, not just the works
08

The traps that blow budgets

  • Scope creep: the spec you price is the spec you hold — upgrades mid-job cost double
  • Deposits: materials up front is normal; big labour deposits are not — pay against completed stages
  • Day rates without a defined scope drift; fixed price against a written spec wherever possible
  • Opening-up surprises: old properties hide their problems behind plasterboard — that's the contingency's job, not the budget's
  • Lead times: kitchens, windows and steels are ordered items — order dates belong in the programme before work starts
  • The cheapest quote is usually the most expensive one by completion — mid-priced, recommended, and busy is the sweet spot